TESTING BATTERY AT ABU SAFA OFFSHORE
Project Information
Project Name | Testing & Commissioning ABU SAFA OFFSHORE |
---|---|
End User | Saudi Aramco |
Contractor | Shore Waves Trading Est |
System | 24 V Battery Charger and Battery Bank |
Location | Outdoor, Abu Safa Offshore |
Status | Ongoing |
Year of Completion | 2020 |
No. of System Comm. | 9 |
Scope Of Work | Installation, Testing & Commissioning |
Activity | Torque, Electrolyte filling and Charging |
Charger | Loop check, Energization and Functional check of Battery Charger including Alarms interfacing with RTU system |
Batteries Test | Load based discharge capacity test Of Ni-cd Batteries |
Interconnection | Interconnection of Cables for all batteries and Tap changer cable connection on correct battery |